Friday, May 15, 2015

SHORT TERM LOOK AHEAD - Week of 05/18/2015 to 05/22/2015

Noise Level Scale:        1          2          3          4          5       
                                                                      

**Coordination with GRCC managers will occur prior to commencement of invasive work and scheduled system shutdowns**


GRCC DATA CENTER RENOVATION:  Noise Level – 1  
-  Switch the new Liebert cooling unit over to be the primary unit.

GRCC M-TEC Renovation:  Noise Level – 1 
-  Remove and replace carpet in Rooms 106, 111 and 118.

Here are some pictures from the concrete placement at M-TEC:








Friday, April 24, 2015

SHORT TERM LOOK AHEAD - Week of 04/27/2015 to 05/01/2015

Noise Level Scale:        1          2          3          4          5       
                                                                      

**Coordination with GRCC managers will occur prior to commencement of invasive work and scheduled system shutdowns**


GRCC DATA CENTER RENOVATION:  Noise Level – 1  
-  The "front face" of the project is complete and furniture is being moved into the space.  This will continue next week. 
-  We have approval for Temporary Occupancy.  We will schedule an inspection for Final Occupancy after all Liebert and UPS are installed.
-  Install tile floor in Kitchen.





Monday, April 20, 2015

SHORT TERM LOOK AHEAD - Week of 04/20/2015 to 04/24/2015

Noise Level Scale:        1          2          3          4          5       
                                                                      

**Coordination with GRCC managers will occur prior to commencement of invasive work and scheduled system shutdowns**


GRCC DATA CENTER RENOVATION:  Noise Level – 1  
-  Electrical finishing up with new light fixtures exit lighting and inspections.
-  Mechanical installing new VAV’S and retrofitting existing the VAV’S. 
-  Ceiling work tile is cut in waiting to put full tile in until above ceiling inspection is complete.
-  Flooring starting Monday hopefully wrapping up by Thursday. 
-  Painting we are about half done hopefully to finish up by Thursday. 
-  We have an above ceiling inspection Tuesday between 10 and 12. With the building inspector. Working towards our temporary occupancy.

Tuesday, April 14, 2015

GRCC DATA CENTER RENOVATION SHORT TERM LOOK AHEAD Week of 04/13/2015 to 04/17/2015



 

 

      

 

GRCC DATA CENTER RENOVATION

SHORT TERM LOOK AHEAD

Week of 04/13/2015 to 04/17/2015

 

 

Noise Level Scale:        1          2          3          4          5       

                                    MPj04331600000[1]       MPj04331600000[1]       MPj04331610000[1]       MPj04331610000[1]       MPj04331610000[1]      

 

**Coordination with GRCC managers will occur prior to commencement of invasive work and scheduled system shutdowns**

 

 

GRCC DATA CENTER RENOVATION:  Noise Level – 1  MPj04331600000[1]

  • Install fixtures toward end of week (Thursday/Friday).

  • Work on mounting main disconnect in transformer vault.

  • Temp feed boiler Checks (remove from panel lpd, will check with GRCC's Team).

  • Schedule shutdowns for mdp, lpa, lpd, p-1 panels.

  • The M-TEC staff and faculty have revised their schedule to install new flooring at the Tassell MTEC (attached) as they are apprehensive about the academic workload that takes place at the end of the semester.

  • For the most part the grid reworking is complete. There were a couple areas our guy said he couldn't match the alteration plan exactly because of various reasons (HVAC equipment in the way of hangers etc.) We will  propose some optimum solution.

  • Office 5: Can the lights be moved one tile towards the door?

  • Office 7: Same as above

  • Hallway outside of Women's Restroom: Can the light be moved one tile in either direction? Doesn't matter which.

  • Let me know if any of these will work. If office 5/7 new layout doesn't work, we can make your layout work, but he would pretty much have to take the whole grid down in that room and start over.

  • Flooring and painting work will continue as schedule permits for trade to work in the same areas.

 

 

 

Grid re-work in areas listed: Rooms:1,2,3,5,6,7,8,9,12,14,15, corridors and reception area.