Noise Level Scale: 1 2 3 4 5
**Coordination with GRCC managers will occur prior to commencement of invasive work and scheduled system shutdowns**
- Electrical finishing up with new light fixtures exit lighting
and inspections.
- Mechanical installing new VAV’S and retrofitting existing the
VAV’S.
- Ceiling work tile is cut in waiting to put full tile in until above
ceiling inspection is complete.
- Flooring starting Monday hopefully wrapping up
by Thursday.
- Painting we are about half done hopefully to finish up by
Thursday.
- We have an above ceiling inspection Tuesday between 10 and 12. With
the building inspector. Working towards our temporary occupancy.