Friday, April 3, 2015

GRCC DATA CENTER RENOVATION SHORT TERM LOOK AHEAD Week of 04/06/2015 to 04/10/2015

 

 

      

 

GRCC DATA CENTER RENOVATION

SHORT TERM LOOK AHEAD

Week of 04/06/2015 to 04/10/2015

 

 

Noise Level Scale:        1          2          3          4          5       

                                    MPj04331600000[1]       MPj04331600000[1]       MPj04331610000[1]       MPj04331610000[1]       MPj04331610000[1]      

 

**Coordination with GRCC managers will occur prior to commencement of invasive work and scheduled system shutdowns**

 

 

GRCC DATA CENTER RENOVATION:  Noise Level – 1  MPj04331600000[1]

  • Monday finish any piping and ductwork rough-in that may be remaining.

  • Tuesday plan to begin cutting out the old reheat valves and preparing for the new reheat valves. Anticipated receiving the new valves by Thursday and completing installation by the end of the day Friday.

  • Above ceiling work on lighting devices office area.

  • Branch wire for lighting.

  • Server room above ceiling/fire alarm.

  • Fire alarm cabling.

  • Electric room new switchgear layout/piping.

  • End of week light fixtures?????

  • Hope to have dates for ups/switchgear for shutdowns soon.

 

 

 

 

Grid re-work in areas listed: Rooms:1,2,3,5,6,7,8,9,12,14,15, corridors and reception area.

 

 

 

 

 

 

 

 

 

      

 

GRCC DATA CENTER RENOVATION

SHORT TERM LOOK AHEAD

Week of 04/06/2015 to 04/10/2015

 

 

Noise Level Scale:        1          2          3          4          5       

                                    MPj04331600000[1]       MPj04331600000[1]       MPj04331610000[1]       MPj04331610000[1]       MPj04331610000[1]      

 

**Coordination with GRCC managers will occur prior to commencement of invasive work and scheduled system shutdowns**

 

 

GRCC DATA CENTER RENOVATION:  Noise Level – 1  MPj04331600000[1]

  • Monday finish any piping and ductwork rough-in that may be remaining.

  • Tuesday plan to begin cutting out the old reheat valves and preparing for the new reheat valves. Anticipated receiving the new valves by Thursday and completing installation by the end of the day Friday.

  • Above ceiling work on lighting devices office area.

  • Branch wire for lighting.

  • Server room above ceiling/fire alarm.

  • Fire alarm cabling.

  • Electric room new switchgear layout/piping.

  • End of week light fixtures?????

  • Hope to have dates for ups/switchgear for shutdowns soon.

 

 

 

 

Grid re-work in areas listed: Rooms:1,2,3,5,6,7,8,9,12,14,15, corridors and reception area.

 

 

 

 

 

 

 

 

 