Monday, March 30, 2015

SHORT TERM LOOK AHEAD - Week of 03/30/2015 to 04/03/2015


Noise Level Scale:        1          2          3          4          5       
                                                                      

**Coordination with GRCC managers will occur prior to commencement of invasive work and scheduled system shutdowns**


GRCC DATA CENTER RENOVATION:  Noise Level – 1 
                Ceiling grid repair
                Painting to start in Offices
                Carpet to follow painting (all carpet to be protected and covered with plastic)
                Rough-in hot water lines (drain, add new valves and tees)

Early Look Ahead For the Week of 04/06/2014:
                Start Fire Alarm on April 6th
Light fixtures ship on April 10th