Noise Level Scale: 1 2 3 4 5
**Coordination with GRCC managers will occur prior to commencement of invasive work and scheduled system shutdowns**
Ceiling grid repair
Painting to start in Offices
Carpet to follow painting (all carpet to be protected and covered with plastic)
Rough-in hot water lines (drain, add new valves and tees)
Early Look Ahead For the Week of 04/06/2014:
Start Fire Alarm on April 6th
Light fixtures ship on April 10th