Friday, April 24, 2015
SHORT TERM LOOK AHEAD - Week of 04/27/2015 to 05/01/2015
Monday, April 20, 2015
SHORT TERM LOOK AHEAD - Week of 04/20/2015 to 04/24/2015
Tuesday, April 14, 2015
GRCC DATA CENTER RENOVATION SHORT TERM LOOK AHEAD Week of 04/13/2015 to 04/17/2015
GRCC DATA CENTER RENOVATION
SHORT TERM LOOK AHEAD
Week of 04/13/2015 to 04/17/2015
Noise Level Scale: 1 2 3 4 5
**Coordination with GRCC managers will occur prior to commencement of invasive work and scheduled system shutdowns**
GRCC DATA CENTER RENOVATION: Noise Level – 1
Install fixtures toward end of week (Thursday/Friday).
Work on mounting main disconnect in transformer vault.
Temp feed boiler Checks (remove from panel lpd, will check with GRCC's Team).
Schedule shutdowns for mdp, lpa, lpd, p-1 panels.
The M-TEC staff and faculty have revised their schedule to install new flooring at the Tassell MTEC (attached) as they are apprehensive about the academic workload that takes place at the end of the semester.
For the most part the grid reworking is complete. There were a couple areas our guy said he couldn't match the alteration plan exactly because of various reasons (HVAC equipment in the way of hangers etc.) We will propose some optimum solution.
Office 5: Can the lights be moved one tile towards the door?
Office 7: Same as above
Hallway outside of Women's Restroom: Can the light be moved one tile in either direction? Doesn't matter which.
Let me know if any of these will work. If office 5/7 new layout doesn't work, we can make your layout work, but he would pretty much have to take the whole grid down in that room and start over.
Flooring and painting work will continue as schedule permits for trade to work in the same areas.
Grid re-work in areas listed: Rooms:1,2,3,5,6,7,8,9,12,14,15, corridors and reception area.
Friday, April 3, 2015
GRCC DATA CENTER RENOVATION SHORT TERM LOOK AHEAD Week of 04/06/2015 to 04/10/2015
GRCC DATA CENTER RENOVATION
SHORT TERM LOOK AHEAD
Week of 04/06/2015 to 04/10/2015
Noise Level Scale: 1 2 3 4 5
**Coordination with GRCC managers will occur prior to commencement of invasive work and scheduled system shutdowns**
GRCC DATA CENTER RENOVATION: Noise Level – 1
Monday finish any piping and ductwork rough-in that may be remaining.
Tuesday plan to begin cutting out the old reheat valves and preparing for the new reheat valves. Anticipated receiving the new valves by Thursday and completing installation by the end of the day Friday.
Above ceiling work on lighting devices office area.
Branch wire for lighting.
Server room above ceiling/fire alarm.
Fire alarm cabling.
Electric room new switchgear layout/piping.
End of week light fixtures?????
Hope to have dates for ups/switchgear for shutdowns soon.
Grid re-work in areas listed: Rooms:1,2,3,5,6,7,8,9,12,14,15, corridors and reception area.
GRCC DATA CENTER RENOVATION
SHORT TERM LOOK AHEAD
Week of 04/06/2015 to 04/10/2015
Noise Level Scale: 1 2 3 4 5
**Coordination with GRCC managers will occur prior to commencement of invasive work and scheduled system shutdowns**
GRCC DATA CENTER RENOVATION: Noise Level – 1
Monday finish any piping and ductwork rough-in that may be remaining.
Tuesday plan to begin cutting out the old reheat valves and preparing for the new reheat valves. Anticipated receiving the new valves by Thursday and completing installation by the end of the day Friday.
Above ceiling work on lighting devices office area.
Branch wire for lighting.
Server room above ceiling/fire alarm.
Fire alarm cabling.
Electric room new switchgear layout/piping.
End of week light fixtures?????
Hope to have dates for ups/switchgear for shutdowns soon.
Grid re-work in areas listed: Rooms:1,2,3,5,6,7,8,9,12,14,15, corridors and reception area.